Wednesday 22 September 2010

| No Comments | No TrackBacks
Awake: 6:29am Temp 62 sleep 6+57 sunny...late afternoon rain overnight @ Nicktown.

After our KK meeting, Kathy, Debra & I got a good workout for (1.7) hrs @ the community center. Back @ our home & on the job sight, the workers are nearly finished building the wall forms...& the concrete trucks (6) are scheduled for 2:00pm today.

Meanwhile, the biggest boom truck I've ever seen arrived: DSC09940.JPG I think that boom has a reach of (90) feet. DSC09941.JPG About (45) min later, the concrete trucks began arriving. DSC09951.JPG The concrete truck feeds the boom hopper with concrete & that is fed into the boom. DSC09944.JPG This worker is spraying a mixture of diesel fuel & detergent onto the aluminum forms which will allow the forms to release easier when the concrete is dried & forms removed. DSC09942.JPG Here the worker has a 2x2 board standing by to tamp down the concrete. DSC09948.JPG This fellow used a remote control device to maneuver the boom. DSC09947.JPG Up to now, it has been a beautiful day for pouring cement...however, late afternoon, dark clouds moved into our area mighty fast. The workers were pouring the last section of the wall when.... DSC09953.JPG the rain, thunder & lighting arrived & the guys started running for cover. DSC09954.JPG The boom operator began bringing down the boom as a precaution....and just in the nick of time: One could barely see to run. DSC09955.JPG A fast moving front it was, with strong winds & heavy rain for not more than (10) min. An hr later, sunshine with a little drizzle & calm winds.

The workers spent another few hrs making sure all that concrete was tampered down & blocked with a (6) inch width of Styrofoam.

Dinner: slice of leftover pizza for each, (2) bowls of New England clam chowder, oyster crackers, garlic toast & an a orange.

After dinner, Zack called us while driving home from work in Seattle. We discussed their 2006 yr pre-owned Lexus, & when he arrived home, we continued talking about the up & coming wedding preparations. Kathy had her list of potential guests & compared that with Zack's list. We spent (1.5) hrs on this phone call with most of that being good business.

Lights out: 11:43pm.

No TrackBacks

TrackBack URL: http://blogs.kirsch.org/mt/mt-tb.cgi/3517

Leave a comment

Categories

Monthly Archives

About this Entry

This page contains a single entry by George Monte Kirsch published on September 25, 2010 8:37 AM.

Tuesday 21 September 2010 was the previous entry in this blog.

Thursday 23 September 2010 is the next entry in this blog.

Find recent content on the main index or look in the archives to find all content.